Dgs Heights, Goregaon East

by D.G.Builders · Goregaon East, Mumbai 400063 · Map

Launched
Jun 20171 yr 6 mths originally promised
Possession (MahaRERA)
Apr 2020Extended by 1 yr 4 mths
Concrete structure
7%Mid-construction
Booked
31 of 3394%
Buildings
10.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
5
1 BHK
15
2 BHK
9
Other units
4
Total units
33
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)7%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 7%Dec 2025: Concrete structure (RCC) 7%Jul 2026: Concrete structure (RCC) 7%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 7%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%7%0%31
100%7%0%31
100%7%0%25

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Dgs Heights by D.G.Builders is a 33-unit BMC-sanctioned project in Goregaon East, Mumbai 400063, launched in June 2017 with possession due in April 2020. 31 units booked out of total 33 units. The concrete structure (RCC) is 7% complete.

Read full summary

Dgs Heights is a BMC-sanctioned project by D.G.Builders in Goregaon East, Mumbai 400063, registered with MahaRERA as P51800000052. It was launched in June 2017. It has 33 units in 1 building: 29 homes (1 RK, 1 BHK and 2 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in April 2020, after an extension of 1 year 4 months from the original December 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 7% complete, final finishes not started.

31 units booked out of total 33 units (94%).