Runwal Elina, Chandivali

Ready to move

by Runwal Developers Private Limited · Chandivali, Mumbai 400072 · Map

Launched
Jun 2017First of 2 phases
Completed (MahaRERA)
Oct 2026Completion reported
Concrete structure
–Weighted across 2 phases
Booked
–
Buildings
41.1 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
2
2 BHK
101
3 BHK
49
Total units
152
Buildings
4
Land
1.1 acres
Phases
2
MahaRERA complaints
2

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Runwal Elina
Completed
P51800000072126––
Runwal Elina Wing C
Completed
P5180001750226100%–
Show updates by phase

Runwal Elina (P51800000072)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%67%67%–
100%67%67%–
100%67%67%91

"–" means MahaRERA shows no figure for that update.

Runwal Elina Wing C (P51800017502)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%–
100%100%100%–
100%100%100%26

"–" means MahaRERA shows no figure for that update.

About this project

Runwal Elina by Runwal Developers Private Limited is a 152-unit project in Chandivali, Mumbai 400072, launched in June 2017 and completed on MahaRERA (completion reported October 2026).

Read full summary

Runwal Elina is a project by Runwal Developers Private Limited in Chandivali, Mumbai 400072, registered with MahaRERA as 2 phases (P51800000072, P51800017502). The first phase was launched in June 2017. Together the phases have 152 units in 4 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Both phases are completed on MahaRERA.

All phases are completed on MahaRERA; both phases have an extended possession date.