Livsmart Kurla, Kurla West

by D. K. Realty (India) Pvt Ltd · Kurla West, Mumbai 400070 · Map

Launched
Jul 20174 yrs 5 mths originally promised
Possession (MahaRERA)
Mar 2028Extended by 6 yrs 3 mths
Concrete structure
7%Mid-construction
Booked
572 of 1,70334% · 570 in Jul 2026
Buildings
284.6 acres
MahaRERA complaints
23Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
850
2 BHK
844
Other units
9
Total units
1,703
Buildings
28
Land
4.6 acres
Phases
1
MahaRERA complaints
23

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)7%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 51%Dec 2025: Concrete structure (RCC) 51%Jul 2026: Concrete structure (RCC) 7%Oct 2026: Concrete structure (RCC) 7%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 7%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%7%0%572
100%7%0%570
100%51%0%570
100%51%0%861

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Livsmart Kurla by D. K. Realty (India) Pvt Ltd is a 1,703-unit SRA-sanctioned project in Kurla West, Mumbai 400070, launched in July 2017 with possession due in March 2028. 572 units booked out of total 1,703 units. The concrete structure (RCC) is 7% complete.

Read full summary

Livsmart Kurla is an SRA-sanctioned project by D. K. Realty (India) Pvt Ltd in Kurla West, Mumbai 400070, registered with MahaRERA as P51800000340. It was launched in July 2017. It has 1,703 units in 28 buildings: 1,694 homes (1 and 2 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2028, extended by 6 years 3 months from the original December 2021. Construction: excavation complete, structure (RCC) 7% complete, final finishes not started.

572 units booked out of total 1,703 units (34%). Since the July 2026 update, 2 more units have been booked.