Kalpataru Radiance, Goregaon West
Ready to move
by Keyana Estate LLP · Goregaon West, Mumbai 400104 · Map
- Launched
- Jul 2017First of 5 phases
- Completed (MahaRERA)
- Oct 2026Completion reported
- Concrete structure
- 100%Weighted across 5 phases
- Booked
- –
- Buildings
- 70.6 acres
- MahaRERA complaints
- 123Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 221
- 3 BHK
- 445
- 4 BHK
- 31
- Other units
- 104
- Total units
- 801
- Buildings
- 7
- Land
- 0.6 acres
- Phases
- 5
- MahaRERA complaints
- 123
The 5 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Kalpataru Radiance C Completed | P51800000482 | 182 | 100% | – | |
| Kalpataru Radiance D Completed | P51800000579 | 182 | 100% | – | |
| Kalpataru Radiance A Completed | P51800000591 | 151 | 100% | – | |
| Kalpataru Radiance B Completed | P51800000810 | 182 | 100% | – | |
| Kalpataru Radiance E Completed | P51800013245 | 0 | 100% | – |
Show updates by phase
Kalpataru Radiance C (P51800000482)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 80% | – | |
| 100% | 100% | 80% | – | |
| 100% | 100% | 80% | 130 |
"–" means MahaRERA shows no figure for that update.
Kalpataru Radiance D (P51800000579)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 79% | – | |
| 100% | 100% | 79% | – | |
| 100% | 100% | 79% | 134 |
"–" means MahaRERA shows no figure for that update.
Kalpataru Radiance A (P51800000591)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 84% | – | |
| 100% | 100% | 84% | – | |
| 100% | 100% | 84% | 123 |
"–" means MahaRERA shows no figure for that update.
Kalpataru Radiance B (P51800000810)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | 149 |
"–" means MahaRERA shows no figure for that update.
Kalpataru Radiance E (P51800013245)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 100% | 0% | – | |
| 0% | 100% | 0% | – | |
| 0% | 100% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Kalpataru Radiance by Keyana Estate LLP (Kalpataru) is an 801-unit project in Goregaon West, Mumbai 400104, launched in July 2017 and completed on MahaRERA (completion reported October 2026).
Read full summary
Kalpataru Radiance is a project by Keyana Estate LLP in Goregaon West, Mumbai 400104, registered with MahaRERA as 5 phases (P51800000482, P51800000579, P51800000591, P51800000810, P51800013245). The first phase was launched in July 2017. Together the phases have 801 units in 7 buildings: 697 homes (2, 3 and 4 BHK) and 104 other units (shops, offices or not given by type), as registered with MahaRERA. All 5 phases are completed on MahaRERA.
All phases are completed on MahaRERA; all 5 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 72% complete. All 5 phases have their structure complete.