Ekta Tripolis, Goregaon West
by Ekta Everglade Homes Private Limited · Goregaon West, Mumbai 400104 · Map
- Launched
- Jul 2017First of 2 phases
- Possession (MahaRERA)
- Apr 2027Extended in both phases
- Concrete structure
- 100%Weighted across 2 phases
- Booked
- –
- Buildings
- 30.7 acres
- MahaRERA complaints
- 83Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 184
- 3 BHK
- 419
- 4 BHK
- 2
- Other units
- 63
- Total units
- 668
- Buildings
- 3
- Land
- 0.7 acres
- Phases
- 2
- MahaRERA complaints
- 83
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Ekta Tripolis Phase I Completed | P51800000947 | 405 | 100% | – | |
| Ekta Tripolis Phase II Ready to move | P51800000731 | 200 | 100% | 94% |
Show updates by phase
Ekta Tripolis Phase I (P51800000947)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 80% | – | |
| 100% | 100% | 80% | – | |
| 100% | 100% | 80% | 409 |
"–" means MahaRERA shows no figure for that update.
Ekta Tripolis Phase II (P51800000731)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 213 | |
| 100% | 100% | 100% | 182 | |
| 100% | 100% | 100% | 182 | |
| 100% | 100% | 40% | 163 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Ekta Tripolis by Ekta Everglade Homes Private Limited is a 668-unit BMC-sanctioned project in Goregaon West, Mumbai 400104, registered with MahaRERA in 2 phases, with possession due in April 2027. The concrete structure (RCC) is complete.
Read full summary
Ekta Tripolis is a BMC-sanctioned project by Ekta Everglade Homes Private Limited in Goregaon West, Mumbai 400104, registered with MahaRERA as 2 phases (P51800000731, P51800000947). The first phase was launched in July 2017. Together the phases have 668 units in 3 buildings: 605 homes (2, 3 and 4 BHK) and 63 other units (shops, offices or not given by type), as registered with MahaRERA. On MahaRERA, 1 is active and 1 is completed.
The registered possession date is April 2027; both phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 87% complete. Both phases have their structure complete.
Ekta's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 8 |
|---|---|
| Total units across these projects | 831 |
| Completed without extending the possession date | 3 |
| Completed after an extension | 3 |
| Lapsed | 0 |
| Under construction | 2 |
| Possession date extended on the builder's application | 4 |
| Typical time from launch to 100% structure | 7 years 5 months |
| MahaRERA complaints (filed by or against the builder), all Ekta projects | 85 (4 of 8 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.