Aventus Heights, Govandi
by Ratnaakar Shelters LLP · Govandi, Mumbai 400043 · Map
- Launched
- Jul 2017First of 2 phases
- Possession (MahaRERA)
- Dec 2024 – Dec 2027Not extended
- Concrete structure
- 90%Weighted across 2 phases
- Booked
- –
- Buildings
- 31.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 160
- 2 BHK
- 203
- Other units
- 47
- Total units
- 410
- Buildings
- 3
- Land
- 1.1 acres
- Phases
- 2
- MahaRERA complaints
- 0
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Aventus Heights Ready to move Lapsed | P51800000858 | 175 | 100% | – | |
| Aventus Heights - Phase 2 Mid-construction | P51800047961 | 188 | 80% | 41% |
Show updates by phase
Aventus Heights (P51800000858)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | 172 |
"–" means MahaRERA shows no figure for that update.
Aventus Heights - Phase 2 (P51800047961)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 80% | 10% | 78 | |
| 100% | 80% | 10% | 78 | |
| 100% | 60% | 10% | 52 | |
| 50% | 50% | 0% | 17 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Aventus Heights by Ratnaakar Shelters LLP is a 410-unit SRA-sanctioned project in Govandi, Mumbai 400043, registered with MahaRERA in 2 phases, with possession dates from December 2024 to December 2027. The concrete structure (RCC) is 90% complete.
Read full summary
Aventus Heights is an SRA-sanctioned project by Ratnaakar Shelters LLP in Govandi, Mumbai 400043, registered with MahaRERA as 2 phases (P51800000858, P51800047961). The first phase was launched in July 2017. Together the phases have 410 units in 3 buildings: 363 homes (1 and 2 BHK) and 47 other units (shops, offices or not given by type), as registered with MahaRERA. On MahaRERA, 1 is lapsed and 1 is active.
The phases' registered possession dates run from December 2024 to December 2027; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 90% complete and final finishes 49% complete. Neither phase has its structure complete.