India International Tower (A6) - upto 13th Floor, Ghatkopar East
by Rare Townships Private Limited · Ghatkopar East, Mumbai 400077 · Map
- Launched
- Jul 20179 yrs 5 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 1 yr
- Concrete structure
- 100%Nearing possession
- Booked
- 55 of 10055% · 45 in Jul 2026
- Buildings
- 11.1 acres
- MahaRERA complaints
- 19Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 52
- 3 BHK
- 48
- Total units
- 100
- Buildings
- 1
- Land
- 1.1 acres
- Phases
- 1
- MahaRERA complaints
- 19
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 70% | 55 | |
| 100% | 100% | 10% | 45 | |
| 100% | 100% | 0% | 49 | |
| 100% | 36% | 0% | 52 |
"–" means MahaRERA shows no figure for that update.
About this project
India International Tower (A6) - upto 13th Floor by Rare Townships Private Limited is a 100-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in July 2017 with possession due in December 2027. 55 units booked out of total 100 units. The concrete structure (RCC) is complete.
Read full summary
India International Tower (A6) - upto 13th Floor is a BMC-sanctioned project by Rare Townships Private Limited in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800001034. It was launched in July 2017. It has 100 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, extended by 1 year from the original December 2026. Construction: excavation complete, structure (RCC) complete, final finishes 70% complete.
55 units booked out of total 100 units (55%). Since the July 2026 update, 10 more units have been booked.
Rare Townships's track record in Mumbai
MahaRERA projects registered 2017–2017 in Mumbai
| Projects registered with MahaRERA | 17 |
|---|---|
| Total units across these projects | 782 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 15 |
| Lapsed | 0 |
| Under construction | 2 |
| Possession date extended on the builder's application | 17 |
| Typical time from launch to 100% structure | 8 years 5 months |
| MahaRERA complaints (filed by or against the builder), all Rare Townships projects | 215 (15 of 17 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.