Navkar Devdatt, Borivali West
by Muktistar Realtors · Borivali West, Mumbai 400092 · Map
- Launched
- Jul 20176 yrs 5 mths originally promised
- Possession (MahaRERA)
- Dec 2028Extended by 5 yrs
- Concrete structure
- 60%Mid-construction
- Booked (free sale)
- –No units for sale
- Buildings
- 10.4 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free saleNo units for sale
Rehab2 units for existing members
Total 2 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 2
- Total units
- 2
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 2
- Free-sale units
- 0
- Rehab units
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 60% | 55% | 26 | |
| 100% | 60% | 55% | 0 | |
| 100% | 60% | 55% | – | |
| 100% | 60% | 55% | 26 |
"–" means MahaRERA shows no figure for that update.
About this project
Navkar Devdatt by Muktistar Realtors is a 2-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in July 2017 with possession due in December 2028. No units for sale: rehab units only. The concrete structure (RCC) is 60% complete.
Read full summary
Navkar Devdatt is a BMC-sanctioned project by Muktistar Realtors in Borivali West, Mumbai 400092, registered with MahaRERA as P51800001177. It was launched in July 2017. It has 2 units in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 2 units, none is for sale and 2 are rehab units for existing members.
Its registered possession date is December 2028, extended by 5 years from the original December 2023. Construction: excavation complete, structure (RCC) 60% complete, final finishes 55% complete.
No units for sale: rehab units only.