Skip to main content

India International Tower (A6) - 14th to 19th floor, Ghatkopar East

by Rare Townships Private Limited · Ghatkopar East, Mumbai 400077 · Map

Launched
Jul 20179 yrs 5 mths originally promised
Possession (MahaRERA)
Dec 2027Extended by 1 yr
Concrete structure
100%Nearing possession
Booked
36 of 4875% · 20 in Jul 2026
Buildings
10.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
24
3 BHK
24
Total units
48
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services40%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 10%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 10%Oct 2026: Final finishes 40%Excavation 100%Concrete structure (RCC) 100%Final finishes 40%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%40%36
100%100%10%20
0%10%0%8
0%0%0%12

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

India International Tower (A6) - 14th to 19th floor by Rare Townships Private Limited is a 48-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in July 2017 with possession due in December 2027. 36 units booked out of total 48 units. The concrete structure (RCC) is complete.

Read full summary

India International Tower (A6) - 14th to 19th floor is a BMC-sanctioned project by Rare Townships Private Limited in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800001357. It was launched in July 2017. It has 48 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, extended by 1 year from the original December 2026. Construction: excavation complete, structure (RCC) complete, final finishes 40% complete.

36 units booked out of total 48 units (75%). Since the July 2026 update, 16 more units have been booked.

Rare Townships's track record in Mumbai

MahaRERA projects registered 2017–2017 in Mumbai

Projects registered with MahaRERA17
Total units across these projects782
Completed without extending the possession date0
Completed after an extension15
Lapsed0
Under construction2
Possession date extended on the builder's application17
Typical time from launch to 100% structure8 years 5 months
MahaRERA complaints (filed by or against the builder), all Rare Townships projects215 (15 of 17 projects)

See all Rare Townships projects →