Elanza Commercial, Ghatkopar West

by Acme Complex Pvt Ltd · Ghatkopar West, Mumbai 400086 · Map

Launched
Jul 20172 yrs 5 mths originally promised
Possession (MahaRERA)
Apr 2028Extended by 8 yrs 4 mths
Concrete structure
100%Nearing possession
Booked
11 of 1573% · 6 in Jul 2026
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
15
Total units
15
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services25%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Jul 2026Oct 2026Dec 2024: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 80%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 25%Excavation 100%Concrete structure (RCC) 100%Final finishes 25%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%25%11
100%80%0%6
100%80%0%6

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Elanza Commercial by Acme Complex Pvt Ltd is a 15-unit BMC-sanctioned project in Ghatkopar West, Mumbai 400086, launched in July 2017 with possession due in April 2028. 11 units booked out of total 15 units. The concrete structure (RCC) is complete.

Read full summary

Elanza Commercial is a BMC-sanctioned project by Acme Complex Pvt Ltd in Ghatkopar West, Mumbai 400086, registered with MahaRERA as P51800001479. It was launched in July 2017. It has 15 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2028, extended by 8 years 4 months from the original December 2019. Construction: excavation complete, structure (RCC) complete, final finishes 25% complete.

11 units booked out of total 15 units (73%). Since the July 2026 update, 5 more units have been booked, the reported concrete structure (RCC) has gone from 80% to 100% and the possession date has moved from December 2020 to April 2028.