Damji Shamji Corporate Square, Ghatkopar East
by Coronate Constructions · Ghatkopar East, Mumbai 400075 · Map
- Launched
- Jul 2017First of 2 phases
- Possession (MahaRERA)
- Dec 2025Extended in 1 of 2 phases
- Concrete structure
- 100%Weighted across 2 phases
- Booked
- –
- Buildings
- 20.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 253
- Total units
- 253
- Buildings
- 2
- Land
- 0.3 acres
- Phases
- 2
- MahaRERA complaints
- 0
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Damji Shamji Corporate Square - A Wing Completed | P51800001495 | 0 | 100% | – | |
| Damji Shamji Corporate Square - Wing C Ready to move | P51800025317 | 0 | 100% | 93% |
Show updates by phase
Damji Shamji Corporate Square - A Wing (P51800001495)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | 18 |
"–" means MahaRERA shows no figure for that update.
Damji Shamji Corporate Square - Wing C (P51800025317)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 98% | 181 | |
| 100% | 100% | 98% | 175 | |
| 100% | 100% | 97% | 161 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Damji Shamji Corporate Square by Coronate Constructions is a 253-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400075, registered with MahaRERA in 2 phases, with possession due in December 2025. The concrete structure (RCC) is complete.
Read full summary
Damji Shamji Corporate Square is a BMC-sanctioned project by Coronate Constructions in Ghatkopar East, Mumbai 400075, registered with MahaRERA as 2 phases (P51800001495, P51800025317). The first phase was launched in July 2017. Together the phases have 253 units in 2 buildings, as registered with MahaRERA. On MahaRERA, 1 is completed and 1 is active.
The registered possession date is December 2025; 1 of 2 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 75% complete. Both phases have their structure complete.