Karmayog, Andheri West

Ready to move

by Westin Developers Pvt Ltd · Andheri West, Mumbai 400053 · Map

Launched
Jul 201711 mths originally promised
Possession (MahaRERA)
Dec 2025Extended by 7 yrs 6 mths
Concrete structure
100%Ready to move
Booked
8 of 1267%
Buildings
10.2 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
12
Total units
12
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 95%Dec 2025: Final finishes 95%Jul 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%8
100%100%95%8
100%100%95%13

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Karmayog by Westin Developers Pvt Ltd is a 12-unit MHADA-sanctioned project in Andheri West, Mumbai 400053, launched in July 2017 with possession due in December 2025. 8 units booked out of total 12 units. The concrete structure (RCC) is complete.

Read full summary

Karmayog is a MHADA-sanctioned project by Westin Developers Pvt Ltd in Andheri West, Mumbai 400053, registered with MahaRERA as P51800001588. It was launched in July 2017. It has 12 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in December 2025, after an extension of 7 years 6 months from the original June 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

8 units booked out of total 12 units (67%).