Montesouth, Mahalaxmi
by Swayam Realtors & Traders LLP · Mahalaxmi, Mumbai 400011 · Map
- Launched
- Jul 2017First of 5 phases
- Possession (MahaRERA)
- Dec 2023 – Feb 2027Extended in 4 of 5 phases
- Concrete structure
- 100%Weighted across 5 phases
- Booked
- –
- Buildings
- 58.2 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 84
- 3 BHK
- 261
- 4 BHK
- 155
- Total units
- 500
- Buildings
- 5
- Land
- 8.2 acres
- Phases
- 5
- MahaRERA complaints
- 2
The 5 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Montesouth-3 Completed | P51800001681 | 53 | 100% | – | |
| Montesouth-2 Nearing possession Lapsed | P51800001779 | 113 | 100% | – | |
| Montesouth-5 Completed | P51900001346 | 113 | 100% | 92% | |
| Montesouth-1 Completed | P51900001936 | 168 | 100% | – | |
| Montesouth-6 Nearing possession | P51800002818 | 53 | 100% | 79% |
Show updates by phase
Montesouth-3 (P51800001681)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 100% | 75% | – | |
| 0% | 100% | 75% | – | |
| 0% | 100% | 75% | 46 |
"–" means MahaRERA shows no figure for that update.
Montesouth-2 (P51800001779)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 100% | 81% | – | |
| 0% | 100% | 81% | – | |
| 0% | 100% | 81% | 101 |
"–" means MahaRERA shows no figure for that update.
Montesouth-5 (P51900001346)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 100% | 57% | 104 | |
| 0% | 25% | 0% | – | |
| 0% | 25% | 0% | – | |
| 0% | 25% | 0% | 102 |
"–" means MahaRERA shows no figure for that update.
Montesouth-1 (P51900001936)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 81% | – | |
| 100% | 100% | 81% | – | |
| 100% | 100% | 81% | 132 |
"–" means MahaRERA shows no figure for that update.
Montesouth-6 (P51800002818)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 65% | 42 | |
| 100% | 100% | 65% | 42 | |
| 0% | 0% | 0% | 38 | |
| 0% | 0% | 0% | 36 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Montesouth by Swayam Realtors & Traders LLP is a 500-unit BMC-sanctioned project in Mahalaxmi, Mumbai 400011, registered with MahaRERA in 5 phases, with possession dates from December 2023 to February 2027. The concrete structure (RCC) is complete.
Read full summary
Montesouth is a BMC-sanctioned project by Swayam Realtors & Traders LLP in Mahalaxmi, Mumbai 400011, registered with MahaRERA as 5 phases (P51800001681, P51800001779, P51900001346, P51900001936, P51800002818). The first phase was launched in July 2017. Together the phases have 500 units in 5 buildings, with 2, 3 and 4 BHK homes as registered with MahaRERA. On MahaRERA, 3 are completed, 1 is lapsed and 1 is active.
The phases' registered possession dates run from December 2023 to February 2027; 4 of 5 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 73% complete. All 5 phases have their structure complete.