Mantra Marquis, Jogeshwari East
by Acme Realties Private Limited · Jogeshwari East, Mumbai 400060 · Map
- Launched
- Jul 2017First of 2 phases
- Possession (MahaRERA)
- Oct 2027Extended in both phases
- Concrete structure
- 100%Weighted across 2 phases
- Booked
- 294 of 30297% · 297 in Jul 2026
- Buildings
- 28.1 acres
- MahaRERA complaints
- 40Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 149
- 3 BHK
- 153
- Total units
- 302
- Buildings
- 2
- Land
- 8.1 acres
- Phases
- 2
- MahaRERA complaints
- 40
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Mantra Marquis Tower 5 Nearing possession | P51800001690 | 152 | 100% | 97% | |
| Mantra Marquis Tower 4 Nearing possession | P51800002133 | 150 | 100% | 98% |
Show updates by phase
Mantra Marquis Tower 5 (P51800001690)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 65% | 147 | |
| 100% | 100% | 30% | 150 | |
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | 149 |
"–" means MahaRERA shows no figure for that update.
Mantra Marquis Tower 4 (P51800002133)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 65% | 147 | |
| 100% | 100% | 30% | 147 | |
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | 150 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Mantra Marquis by Acme Realties Private Limited is a 302-unit MHADA-sanctioned project in Jogeshwari East, Mumbai 400060, registered with MahaRERA in 2 phases, with possession due in October 2027. 294 units booked out of total 302 units. The concrete structure (RCC) is complete.
Read full summary
Mantra Marquis is a MHADA-sanctioned project by Acme Realties Private Limited in Jogeshwari East, Mumbai 400060, registered with MahaRERA as 2 phases (P51800001690, P51800002133). The first phase was launched in July 2017. Together the phases have 302 units in 2 buildings, with 2 and 3 BHK homes as registered with MahaRERA. Both phases are active on MahaRERA.
The registered possession date is October 2027; both phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 65% complete. Both phases have their structure complete.
294 units booked out of total 302 units (97%).