Royal Green, Andheri East

by Admire Revive Builder & Developer · Andheri East, Mumbai 400059 · Map

Launched
Jul 20174 yrs 5 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 5 yrs
Concrete structure
83%Mid-construction
Booked
94 of 12078%
Buildings
00.3 acres
MahaRERA complaints
4Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
107
2 BHK
13
Total units
120
Buildings
0
Land
0.3 acres
Phases
1
MahaRERA complaints
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)83%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 0%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 83%Dec 2025: Concrete structure (RCC) 83%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 83%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 83%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%83%0%94
0%0%0%–
100%83%0%–
100%83%0%94

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Royal Green by Admire Revive Builder & Developer is a 120-unit project in Andheri East, Mumbai 400059, launched in July 2017 with possession due in December 2026. 94 units booked out of total 120 units. The concrete structure (RCC) is 83% complete.

Read full summary

Royal Green is a project by Admire Revive Builder & Developer in Andheri East, Mumbai 400059, registered with MahaRERA as P51800002086. It was launched in July 2017. It has 120 units, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 5 years from the original December 2021. Construction: excavation complete, structure (RCC) 83% complete, final finishes not started.

94 units booked out of total 120 units (78%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 83%.