Neptune Eleve, Bhandup West
by Neptune Ventures And Developers Private Limited · Bhandup West, Mumbai 400078 · Map
- Launched
- Aug 2017First of 4 phases
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 0%Weighted across 4 phases
- Booked
- 475 of 1,44833%
- Buildings
- 40.2 acres
- MahaRERA complaints
- 19Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 696
- 3 BHK
- 752
- Total units
- 1,448
- Buildings
- 4
- Land
- 0.2 acres
- Phases
- 4
- MahaRERA complaints
- 19
The 4 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Neptune Eleve Wing C Early stage | P51800002428 | 362 | 0% | 34% | |
| Neptune Eleve Wing A Early stage | P51800008544 | 362 | 0% | 52% | |
| Neptune Eleve Wing B Early stage | P51800009976 | 362 | 0% | 42% | |
| Neptune Eleve Wing D Early stage | P51800012220 | 362 | 0% | 4% |
Show updates by phase
Neptune Eleve Wing C (P51800002428)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 10% | 0% | 0% | 122 | |
| 10% | 0% | 0% | – | |
| 10% | 0% | 0% | – | |
| 10% | 0% | 0% | 122 |
"–" means MahaRERA shows no figure for that update.
Neptune Eleve Wing A (P51800008544)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 10% | 0% | 0% | 189 | |
| 10% | 0% | 0% | – | |
| 10% | 0% | 0% | – | |
| 10% | 0% | 0% | 189 |
"–" means MahaRERA shows no figure for that update.
Neptune Eleve Wing B (P51800009976)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 10% | 0% | 0% | 151 | |
| 10% | 0% | 0% | – | |
| 10% | 0% | 0% | – | |
| 10% | 0% | 0% | 151 |
"–" means MahaRERA shows no figure for that update.
Neptune Eleve Wing D (P51800012220)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 10% | 0% | 0% | 13 | |
| 10% | 0% | 0% | – | |
| 10% | 0% | 0% | – | |
| 10% | 0% | 0% | 13 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Neptune Eleve by Neptune Ventures And Developers Private Limited is a 1,448-unit project in Bhandup West, Mumbai 400078, registered with MahaRERA in 4 phases, with possession due in December 2026. 475 units booked out of total 1,448 units. Work on the concrete structure (RCC) has not started.
Read full summary
Neptune Eleve is a project by Neptune Ventures And Developers Private Limited in Bhandup West, Mumbai 400078, registered with MahaRERA as 4 phases (P51800002428, P51800008544, P51800009976, P51800012220). The first phase was launched in August 2017. Together the phases have 1,448 units in 4 buildings, with 2 and 3 BHK homes as registered with MahaRERA. All 4 phases are active on MahaRERA.
The registered possession date is December 2026; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 0% complete and final finishes 0% complete. None of the 4 phases has its structure complete.
475 units booked out of total 1,448 units (33%).
Neptune's track record in Mumbai
MahaRERA projects registered 2017–2018 in Mumbai
| Projects registered with MahaRERA | 7 |
|---|---|
| Total units across these projects | 1,735 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 2 |
| Lapsed | 1 |
| Under construction | 4 |
| Possession date extended on the builder's application | 2 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Neptune projects | 35 (7 of 7 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.