Neumec Srushti, Ghatkopar West

by Neumec Estate Developer LLP · Ghatkopar West, Mumbai 400084 · Map

Launched
Aug 20174 yrs 10 mths originally promised
Possession (MahaRERA)
Apr 2028Extended by 5 yrs 10 mths
Concrete structure
78%Mid-construction
Booked (free sale)
122 of 15877% · 133 rehab units
Buildings
21.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale122 booked out of 158 units

Rehab133 units for existing members

Land-owner share2 units, not for sale

Total 293 units. Rehab and land-owner units are not for sale.

Project facts

1 BHK
248
2 BHK
36
3 BHK
1
Other units
8
Total units
293
Buildings
2
Land
1.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
158
Rehab units
133
Land-owner share (not for sale)
2
Reserved units
11

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)78%
Finishes, lifts and services8%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 90%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 85%Dec 2025: Concrete structure (RCC) 78%Jul 2026: Concrete structure (RCC) 78%Oct 2026: Concrete structure (RCC) 78%Dec 2024: Final finishes 5%Dec 2025: Final finishes 8%Jul 2026: Final finishes 8%Oct 2026: Final finishes 8%Excavation 100%Concrete structure (RCC) 78%Final finishes 8%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%78%8%122
100%78%8%122
100%78%8%122
90%85%5%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Neumec Srushti by Neumec Estate Developer LLP is a 293-unit SRA-sanctioned project in Ghatkopar West, Mumbai 400084, launched in August 2017 with possession due in April 2028. 122 units booked out of 158 units for sale. The concrete structure (RCC) is 78% complete.

Read full summary

Neumec Srushti is an SRA-sanctioned project by Neumec Estate Developer LLP in Ghatkopar West, Mumbai 400084, registered with MahaRERA as P51800002532. It was launched in August 2017. It has 293 units in 2 buildings: 285 homes (1, 2 and 3 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 293 units, 158 are for sale, 133 are rehab units for existing members and 2 are the land-owner's share, not for sale.

Its registered possession date is April 2028, extended by 5 years 10 months from the original June 2022. Construction: excavation complete, structure (RCC) 78% complete, final finishes 8% complete.

122 units booked out of 158 units for sale (77%).