Terraform Dwarka, Ghatkopar East

by Money Magnum Nest Pvt Ltd · Ghatkopar East, Mumbai 400077 · Map

Launched
Aug 2017First of 4 phases
Possession (MahaRERA)
Dec 2027Extended in 2 of 4 phases
Concrete structure
61%Weighted across 4 phases
Booked
–
Buildings
40.6 acres
MahaRERA complaints
8Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
120
2 BHK
124
3 BHK
40
Other units
3
Total units
287
Buildings
4
Land
0.6 acres
Phases
4
MahaRERA complaints
8

The 4 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Terraform Dwarka
Completed
P5180000271867100%–
Terraform Dwarka
Completed
P5180000282655100%–
Terraform Dwarka - Wing C
Mid-construction
P518000206086928%45%
Terraform Dwarka - Wing D
Mid-construction
P518000206669335%38%
Show updates by phase

Terraform Dwarka (P51800002718)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%–
100%100%100%–
100%100%100%51

"–" means MahaRERA shows no figure for that update.

Terraform Dwarka (P51800002826)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%–
100%100%100%–
100%100%100%52

"–" means MahaRERA shows no figure for that update.

Terraform Dwarka - Wing C (P51800020608)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%28%2%31
100%28%2%31
100%28%2%31
100%28%0%31

"–" means MahaRERA shows no figure for that update.

Terraform Dwarka - Wing D (P51800020666)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%35%2%35
100%35%2%35
100%35%2%35
100%37%0%35

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)61%
Finishes, lifts and services44%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 62%Dec 2025: Concrete structure (RCC) 61%Jul 2026: Concrete structure (RCC) 61%Oct 2026: Concrete structure (RCC) 61%Dec 2024: Final finishes 43%Dec 2025: Final finishes 44%Jul 2026: Final finishes 44%Oct 2026: Final finishes 44%Excavation 100%Concrete structure (RCC) 61%Final finishes 44%

How to read construction stages

About this project

Terraform Dwarka by Money Magnum Nest Pvt Ltd is a 287-unit SRA-sanctioned project in Ghatkopar East, Mumbai 400077, registered with MahaRERA in 4 phases, with possession due in December 2027. The concrete structure (RCC) is 61% complete.

Read full summary

Terraform Dwarka is an SRA-sanctioned project by Money Magnum Nest Pvt Ltd in Ghatkopar East, Mumbai 400077, registered with MahaRERA as 4 phases (P51800002718, P51800002826, P51800020608, P51800020666). The first phase was launched in August 2017. Together the phases have 287 units in 4 buildings: 284 homes (1, 2 and 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. On MahaRERA, 2 are completed and 2 are active.

The registered possession date is December 2027; 2 of 4 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 61% complete and final finishes 44% complete. 2 of the 4 phases have their structure complete.