Joy Legend Wing B, Khar West
by Bhavin Jayant Soni · Khar West, Mumbai 400052 · Map
- Launched
- Aug 20172 yrs 4 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 7 yrs 4 mths
- Concrete structure
- 31%Mid-construction
- Booked
- 38 of 8644%
- Buildings
- 10.6 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 3 BHK
- 70
- 4 BHK
- 14
- 5+ BHK
- 2
- Total units
- 86
- Buildings
- 1
- Land
- 0.6 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 31% | 2% | 38 | |
| 100% | 31% | 2% | 38 | |
| 100% | 31% | 2% | 38 | |
| 99% | 15% | 1% | 29 |
"–" means MahaRERA shows no figure for that update.
About this project
Joy Legend Wing B by Bhavin Jayant Soni is an 86-unit SRA-sanctioned project in Khar West, Mumbai 400052, launched in August 2017 with possession due in April 2027. 38 units booked out of total 86 units. The concrete structure (RCC) is 31% complete.
Read full summary
Joy Legend Wing B is an SRA-sanctioned project by Bhavin Jayant Soni in Khar West, Mumbai 400052, registered with MahaRERA as P51800003263. It was launched in August 2017. It has 86 units in 1 building, with 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2027, extended by 7 years 4 months from the original December 2019. Construction: excavation complete, structure (RCC) 31% complete, final finishes 2% complete.
38 units booked out of total 86 units (44%).