Kuldeep-Ishchhaya Chs Ltd, Mulund West
Ready to move
by Tridev Realty And Construction Pvt Ltd · Mulund West, Mumbai 400080 · Map
- Launched
- Aug 20173 yrs 10 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 5 yrs 6 mths
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 33 of 33100% · 36 rehab units
- Buildings
- 10.4 acres
- MahaRERA complaints
- 3Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale33 booked out of 33 units
Rehab36 units for existing members
Total 69 units. Rehab units are not for sale.
Project facts
- 1 RK
- 11
- 1 BHK
- 19
- 2 BHK
- 31
- 3 BHK
- 8
- Total units
- 69
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 3
- Free-sale units
- 33
- Rehab units
- 36
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 33 | |
| 100% | 100% | 95% | 33 | |
| 100% | 100% | 80% | 33 | |
| 100% | 100% | 80% | 33 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400080
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 10 mths | 3 yrs 6 mths |
| Possession date extended | By 5 yrs 6 mths | 6 of 6 |
| Possession date (MahaRERA) | Dec 2026 | Jul 2024 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 100% | 90% |
| MahaRERA complaints (filed by or against the builder) | 3 | 0 |
The 6 projects
- Lijjat Ganga, Mulund West
- Dhoot Pride Residency-Devidayal Apartment, Mulund West
- Shivdham, Mulund West
- Shivam, Mulund West
- Mulund Mahavirdham Co. Op. Housing Soc. Ltd, Mulund West
- Neptunes Lotus, Mulund West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Lijjat Ganga | August 2017 | May 2020 | 98% | 29 units booked out of total 70 units |
| Dhoot Pride Residency-Devidayal Apartment | August 2017 | December 2026 | 100% | 27 units booked out of 32 units for sale |
| Shivdham | August 2017 | March 2022 | 67% | 78 units booked out of total 81 units |
| Shivam | August 2017 | September 2021 | 100% | 78 units booked out of total 81 units |
| Mulund Mahavirdham Co. Op. Housing Soc. Ltd | August 2017 | March 2027 | 100% | 38 units booked out of 38 units for sale |
| Neptunes Lotus | August 2017 | April 2028 | 100% | 49 units booked out of total 61 units |
About this project
Kuldeep-Ishchhaya Chs Ltd by Tridev Realty And Construction Pvt Ltd is a 69-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in August 2017 with possession due in December 2026. 33 units booked out of 33 units for sale. The concrete structure (RCC) is complete.
Read full summary
Kuldeep-Ishchhaya Chs Ltd is a BMC-sanctioned project by Tridev Realty And Construction Pvt Ltd in Mulund West, Mumbai 400080, registered with MahaRERA as P51800003506. It was launched in August 2017. It has 69 units in 1 building, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 69 units, 33 are for sale and 36 are rehab units for existing members.
Its registered possession date is December 2026, extended by 5 years 6 months from the original June 2021. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
33 units booked out of 33 units for sale (100%).