Sky City, Borivali East
by Incline Realty Private Limited · Borivali East, Mumbai 400066 · Map
- Launched
- Aug 2017First of 5 phases
- Possession (MahaRERA)
- Jun 2027 – Jun 2030Not extended
- Concrete structure
- 97%Weighted across 5 phases
- Booked
- –
- Buildings
- 825.2 acres
- MahaRERA complaints
- 6Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 553
- 3 BHK
- 2,520
- Other units
- 500
- Total units
- 3,573
- Buildings
- 8
- Land
- 25.2 acres
- Phases
- 5
- MahaRERA complaints
- 6
- Reserved units
- 472
The 5 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Sky City Towers A to D Completed | P51800003582 | 1,588 | 100% | – | |
| Sky City Tower E Completed | P51800018404 | 324 | 100% | – | |
| Sky City Tower F Nearing possession | P51800028419 | 389 | 100% | 89% | |
| Sky City Tower G Nearing possession | P51800047575 | 462 | 100% | 79% | |
| Sky City Tower H Mid-construction | PR1180002502390 | 310 | 74% | 68% |
Show updates by phase
Sky City Towers A to D (P51800003582)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | 1,512 |
"–" means MahaRERA shows no figure for that update.
Sky City Tower E (P51800018404)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | 305 |
"–" means MahaRERA shows no figure for that update.
Sky City Tower F (P51800028419)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 23% | 352 | |
| 100% | 100% | 15% | 343 | |
| 100% | 100% | 6% | 317 | |
| 100% | 68% | 0% | 313 |
"–" means MahaRERA shows no figure for that update.
Sky City Tower G (P51800047575)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 19% | 367 | |
| 100% | 97% | 9% | 363 | |
| 100% | 100% | 7% | 343 | |
| 100% | 50% | 0% | 317 |
"–" means MahaRERA shows no figure for that update.
Sky City Tower H (PR1180002502390)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 74% | 5% | 530 | |
| 100% | 50% | 4% | 491 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Sky City by Incline Realty Private Limited is a 3,573-unit BMC-sanctioned project in Borivali East, Mumbai 400066, registered with MahaRERA in 5 phases, with possession dates from June 2027 to June 2030. The concrete structure (RCC) is 97% complete.
Read full summary
Sky City is a BMC-sanctioned project by Incline Realty Private Limited in Borivali East, Mumbai 400066, registered with MahaRERA as 5 phases (P51800003582, P51800018404, P51800028419, P51800047575, PR1180002502390). The first phase was launched in August 2017. Together the phases have 3,573 units in 8 buildings: 3,073 homes (1 RK and 3 BHK) and 500 other units (shops, offices or not given by type), as registered with MahaRERA. On MahaRERA, 3 are active and 2 are completed.
The phases' registered possession dates run from June 2027 to June 2030; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 97% complete and final finishes 68% complete. 4 of the 5 phases have their structure complete.