Bhawani Heights, Jogeshwari East
Ready to move
by M/s BHAWANI DEVELOPERS · Jogeshwari East, Mumbai 400060 · Map
- Launched
- Aug 20173 yrs originally promised
- Possession (MahaRERA)
- Jun 2027Extended by 6 yrs 10 mths
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 88 of 9494% · 113 rehab units
- Buildings
- 10.5 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale88 booked out of 94 units
Rehab113 units for existing members
Total 207 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 173
- 2 BHK
- 20
- Other units
- 14
- Total units
- 207
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 2
- Free-sale units
- 94
- Rehab units
- 113
- Reserved units
- 37
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 88 | |
| 100% | 100% | 95% | 88 | |
| 100% | 100% | 90% | 88 | |
| 100% | 72% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Bhawani Heights by M/s BHAWANI DEVELOPERS is a 207-unit SRA-sanctioned project in Jogeshwari East, Mumbai 400060, launched in August 2017 with possession due in June 2027. 88 units booked out of 94 units for sale. The concrete structure (RCC) is complete.
Read full summary
Bhawani Heights is an SRA-sanctioned project by M/s BHAWANI DEVELOPERS in Jogeshwari East, Mumbai 400060, registered with MahaRERA as P51800003807. It was launched in August 2017. It has 207 units in 1 building: 193 homes (1 and 2 BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 207 units, 94 are for sale and 113 are rehab units for existing members.
Its registered possession date is June 2027, extended by 6 years 10 months from the original August 2020. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
88 units booked out of 94 units for sale (94%).