Zee Shaan, Vile Parle East

Ready to move

by Trisul Developers · Vile Parle East, Mumbai 400057 · Map

Launched
Aug 20177 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 2 yrs
Concrete structure
100%Ready to move
Booked
99 of 13374%
Buildings
21.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
133
Total units
133
Buildings
2
Land
1.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 90%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 60%Dec 2025: Final finishes 95%Jul 2026: Final finishes 95%Oct 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%99
100%100%95%99
100%100%95%95
90%100%60%53

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Zee Shaan by Trisul Developers is a 133-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in August 2017 with possession due in December 2026. 99 units booked out of total 133 units. The concrete structure (RCC) is complete.

Read full summary

Zee Shaan is a BMC-sanctioned project by Trisul Developers in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800003892. It was launched in August 2017. It has 133 units in 2 buildings, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 2 years from the original December 2024. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

99 units booked out of total 133 units (74%).