Vijayraj Residency, Vile Parle East
by Vijayraj Realtors · Vile Parle East, Mumbai 400057 · Map
- Launched
- Aug 20176 yrs 11 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 3 yrs 5 mths
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 43 of 7756% · 68 rehab units
- Buildings
- 10.5 acres
- MahaRERA complaints
- 19Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale43 booked out of 77 units
Rehab68 units for existing members
Land-owner share25 units, not for sale
Total 170 units. Rehab and land-owner units are not for sale.
Project facts
- 1 BHK
- 116
- 2 BHK
- 28
- 3 BHK
- 14
- Other units
- 12
- Total units
- 170
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 19
- Free-sale units
- 77
- Rehab units
- 68
- Land-owner share (not for sale)
- 25
- Reserved units
- 5
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 45% | 43 | |
| 100% | 70% | 0% | 42 | |
| 100% | 63% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Vijayraj Residency by Vijayraj Realtors is a 170-unit SRA-sanctioned project in Vile Parle East, Mumbai 400057, launched in August 2017 with possession due in December 2027. 43 units booked out of 77 units for sale. The concrete structure (RCC) is complete.
Read full summary
Vijayraj Residency is an SRA-sanctioned project by Vijayraj Realtors in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800004495. It was launched in August 2017. It has 170 units in 1 building: 158 homes (1, 2 and 3 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 170 units, 77 are for sale, 68 are rehab units for existing members and 25 are the land-owner's share, not for sale.
Its registered possession date is December 2027, extended by 3 years 5 months from the original July 2024. Construction: excavation complete, structure (RCC) complete, final finishes 45% complete.
43 units booked out of 77 units for sale (56%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 70% to 100%.