Nero, Bandra East
by Super Construction Company · Bandra East, Mumbai 400051 · Map
- Launched
- Aug 20173 yrs 10 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 5 yrs 6 mths
- Concrete structure
- 95%Mid-construction
- Booked
- 75 of 9777% · 64 in Jul 2026
- Buildings
- 10.8 acres
- MahaRERA complaints
- 6Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 64
- 3 BHK
- 30
- Other units
- 3
- Total units
- 97
- Buildings
- 1
- Land
- 0.8 acres
- Phases
- 1
- MahaRERA complaints
- 6
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 95% | 40% | 75 | |
| 100% | 90% | 0% | 64 | |
| 100% | 89% | 0% | 51 | |
| 100% | 94% | 0% | 43 |
"–" means MahaRERA shows no figure for that update.
About this project
Nero by Super Construction Company is a 97-unit SRA-sanctioned project in Bandra East, Mumbai 400051, launched in August 2017 with possession due in December 2026. 75 units booked out of total 97 units. The concrete structure (RCC) is 95% complete.
Read full summary
Nero is an SRA-sanctioned project by Super Construction Company in Bandra East, Mumbai 400051, registered with MahaRERA as P51800004508. It was launched in August 2017. It has 97 units in 1 building: 94 homes (2 and 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 5 years 6 months from the original June 2021. Construction: excavation complete, structure (RCC) 95% complete, final finishes 40% complete.
75 units booked out of total 97 units (77%). Since the July 2026 update, 11 more units have been booked, the reported concrete structure (RCC) has gone from 90% to 95% and the possession date has moved from March 2024 to December 2026.