Centrona Nova, Ghatkopar East
by Elevated Avenue Realty LLP · Ghatkopar East, Mumbai 400077 · Map
- Launched
- Aug 2017First of 2 phases
- Possession (MahaRERA)
- Jun 2027Extended in both phases
- Concrete structure
- 69%Weighted across 2 phases
- Booked
- 452 of 45499% · 451 in Jul 2026
- Buildings
- 20.2 acres
- MahaRERA complaints
- 4Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 222
- 2 BHK
- 232
- Total units
- 454
- Buildings
- 2
- Land
- 0.2 acres
- Phases
- 2
- MahaRERA complaints
- 4
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Centrona Nova B Mid-construction | P51800004566 | 228 | 69% | 100% | |
| Centrona Nova-A Mid-construction | P51800005456 | 226 | 69% | 99% |
Show updates by phase
Centrona Nova B (P51800004566)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 69% | 0% | 228 | |
| 90% | 0% | 0% | 228 | |
| 90% | 0% | 0% | 228 | |
| 90% | 0% | 0% | 3 |
"–" means MahaRERA shows no figure for that update.
Centrona Nova-A (P51800005456)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 69% | 0% | 224 | |
| 100% | 29% | 0% | 223 | |
| 100% | 0% | 0% | 221 | |
| 90% | 0% | 0% | 8 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Centrona Nova by Elevated Avenue Realty LLP is a 454-unit SRA-sanctioned project in Ghatkopar East, Mumbai 400077, registered with MahaRERA in 2 phases, with possession due in June 2027. 452 units booked out of total 454 units. The concrete structure (RCC) is 69% complete.
Read full summary
Centrona Nova is an SRA-sanctioned project by Elevated Avenue Realty LLP in Ghatkopar East, Mumbai 400077, registered with MahaRERA as 2 phases (P51800004566, P51800005456). The first phase was launched in August 2017. Together the phases have 454 units in 2 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Both phases are active on MahaRERA.
The registered possession date is June 2027; both phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 69% complete and final finishes 0% complete. Neither phase has its structure complete.
452 units booked out of total 454 units (99%). Since the July 2026 update, 1 more unit has been booked.
Elevated Avenue's track record in Mumbai
MahaRERA projects registered 2017–2019 in Mumbai
| Projects registered with MahaRERA | 7 |
|---|---|
| Total units across these projects | 2,204 |
| Completed without extending the possession date | 1 |
| Completed after an extension | 0 |
| Lapsed | 0 |
| Under construction | 6 |
| Possession date extended on the builder's application | 0 |
| Typical time from launch to 100% structure | 8 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Elevated Avenue projects | 11 (6 of 7 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.