Centrona Nova, Ghatkopar East

by Elevated Avenue Realty LLP · Ghatkopar East, Mumbai 400077 · Map

Launched
Aug 2017First of 2 phases
Possession (MahaRERA)
Jun 2027Extended in both phases
Concrete structure
69%Weighted across 2 phases
Booked
452 of 45499% · 451 in Jul 2026
Buildings
20.2 acres
MahaRERA complaints
4Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
222
2 BHK
232
Total units
454
Buildings
2
Land
0.2 acres
Phases
2
MahaRERA complaints
4

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Centrona Nova B
Mid-construction
P5180000456622869%100%
Centrona Nova-A
Mid-construction
P5180000545622669%99%
Show updates by phase

Centrona Nova B (P51800004566)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%69%0%228
90%0%0%228
90%0%0%228
90%0%0%3

"–" means MahaRERA shows no figure for that update.

Centrona Nova-A (P51800005456)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%69%0%224
100%29%0%223
100%0%0%221
90%0%0%8

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)69%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 90%Dec 2025: Excavation 95%Jul 2026: Excavation 95%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 14%Oct 2026: Concrete structure (RCC) 69%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 69%Final finishes 0%

How to read construction stages

About this project

Centrona Nova by Elevated Avenue Realty LLP is a 454-unit SRA-sanctioned project in Ghatkopar East, Mumbai 400077, registered with MahaRERA in 2 phases, with possession due in June 2027. 452 units booked out of total 454 units. The concrete structure (RCC) is 69% complete.

Read full summary

Centrona Nova is an SRA-sanctioned project by Elevated Avenue Realty LLP in Ghatkopar East, Mumbai 400077, registered with MahaRERA as 2 phases (P51800004566, P51800005456). The first phase was launched in August 2017. Together the phases have 454 units in 2 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Both phases are active on MahaRERA.

The registered possession date is June 2027; both phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 69% complete and final finishes 0% complete. Neither phase has its structure complete.

452 units booked out of total 454 units (99%). Since the July 2026 update, 1 more unit has been booked.

Elevated Avenue's track record in Mumbai

MahaRERA projects registered 2017–2019 in Mumbai

Projects registered with MahaRERA7
Total units across these projects2,204
Completed without extending the possession date1
Completed after an extension0
Lapsed0
Under construction6
Possession date extended on the builder's application0
Typical time from launch to 100% structure8 years 4 months
MahaRERA complaints (filed by or against the builder), all Elevated Avenue projects11 (6 of 7 projects)

See all Elevated Avenue projects →