Satwaratna Co Op Hsg Society Ltd, Chembur
by Kishrajdevelopers · Chembur, Mumbai 400074 · Map
- Launched
- Aug 20173 yrs 1 mth originally promised
- Possession (MahaRERA)
- Jan 2027Extended by 6 yrs 4 mths
- Concrete structure
- 78%Mid-construction
- Booked (free sale)
- 18 of 1995%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale18 booked out of 19 units
Land-owner share12 units, not for sale
Total 31 units. Land-owner units are not for sale.
Project facts
- 1 BHK
- 4
- 2 BHK
- 24
- Other units
- 3
- Total units
- 31
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 19
- Land-owner share (not for sale)
- 12
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 78% | 0% | 18 | |
| 100% | 78% | 0% | 17 | |
| 100% | 50% | 0% | – | |
| 100% | 50% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Satwaratna Co Op Hsg Society Ltd by Kishrajdevelopers is a 31-unit BMC-sanctioned project in Chembur, Mumbai 400074, launched in August 2017 with possession due in January 2027. 18 units booked out of 19 units for sale. The concrete structure (RCC) is 78% complete.
Read full summary
Satwaratna Co Op Hsg Society Ltd is a BMC-sanctioned project by Kishrajdevelopers in Chembur, Mumbai 400074, registered with MahaRERA as P51800004735. It was launched in August 2017. It has 31 units in 1 building: 28 homes (1 and 2 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 31 units, 19 are for sale and 12 are the land-owner's share, not for sale.
Its registered possession date is January 2027, extended by 6 years 4 months from the original September 2020. Construction: excavation complete, structure (RCC) 78% complete, final finishes not started.
18 units booked out of 19 units for sale (95%). Since the July 2026 update, 1 more unit has been booked and the possession date has moved from December 2025 to January 2027.