Shubh Aangan, Bhandup East

Ready to move

by G D Realtors Pvt Ltd · Bhandup East, Mumbai 400042 · Map

Launched
Aug 2017First of 2 phases
Completed (MahaRERA)
Oct 2026Completion reported
Concrete structure
100%Weighted across 2 phases
Booked
–
Buildings
20.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
55
2 BHK
41
3 BHK
7
Other units
3
Total units
106
Buildings
2
Land
0.5 acres
Phases
2
MahaRERA complaints
0

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Shubh Aangan
Completed
P5180000532082100%–
Shubh Aangan Wing B
Completed
P5180002956821100%–
Show updates by phase

Shubh Aangan (P51800005320)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%70%–
100%100%70%–
100%100%70%56

"–" means MahaRERA shows no figure for that update.

Shubh Aangan Wing B (P51800029568)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%–
100%100%100%–
100%100%100%0

"–" means MahaRERA shows no figure for that update.

About this project

Shubh Aangan by G D Realtors Pvt Ltd is a 106-unit project in Bhandup East, Mumbai 400042, launched in August 2017 and completed on MahaRERA (completion reported October 2026).

Read full summary

Shubh Aangan is a project by G D Realtors Pvt Ltd in Bhandup East, Mumbai 400042, registered with MahaRERA as 2 phases (P51800005320, P51800029568). The first phase was launched in August 2017. Together the phases have 106 units in 2 buildings: 103 homes (1, 2 and 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Both phases are completed on MahaRERA.

All phases are completed on MahaRERA; 1 of 2 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 76% complete. Both phases have their structure complete.