Manthan Plaza, Santacruz East

Ready to move

by Manthan Development Corporation · Santacruz East, Mumbai 400055 · Map

Launched
Aug 201710 yrs 4 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
100%Ready to move
Booked
20 of 2969%
Buildings
10.7 acres
MahaRERA complaints
4Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
29
Total units
29
Buildings
1
Land
0.7 acres
Phases
1
MahaRERA complaints
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 97%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 90%Dec 2025: Final finishes 90%Jul 2026: Final finishes 90%Oct 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%20
100%97%90%20
100%100%90%20
100%100%90%16

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Manthan Plaza by Manthan Development Corporation is a 29-unit BMC-sanctioned project in Santacruz East, Mumbai 400055, launched in August 2017 with possession due in December 2027. 20 units booked out of total 29 units. The concrete structure (RCC) is complete.

Read full summary

Manthan Plaza is a BMC-sanctioned project by Manthan Development Corporation in Santacruz East, Mumbai 400055, registered with MahaRERA as P51800005360. It was launched in August 2017. It has 29 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

20 units booked out of total 29 units (69%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 97% to 100%.