A and O EMINENTE, Dahisar

by Ashapura Housing Private Limited · Dahisar, Mumbai 400068 · Map

Launched
Aug 20173 yrs 10 mths originally promised
Possession (MahaRERA)
Apr 2027Extended by 5 yrs 10 mths
Concrete structure
60%Mid-construction
Booked
576 of 576100% · 479 in Dec 2024
Buildings
10.9 acres
MahaRERA complaints
94Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
569
2 BHK
7
Total units
576
Buildings
1
Land
0.9 acres
Phases
1
MahaRERA complaints
94
Reserved units
15

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation93%
Concrete structure (slabs)60%
Finishes, lifts and services15%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Oct 2026Dec 2024: Excavation 93%Oct 2026: Excavation 93%Dec 2024: Concrete structure (RCC) 60%Oct 2026: Concrete structure (RCC) 60%Dec 2024: Final finishes 15%Oct 2026: Final finishes 15%Excavation 93%Concrete structure (RCC) 60%Final finishes 15%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
93%60%15%576
93%60%15%479

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

A and O EMINENTE by Ashapura Housing Private Limited is a 576-unit SRA-sanctioned project in Dahisar, Mumbai 400068, launched in August 2017 with possession due in April 2027. 576 units booked out of total 576 units. The concrete structure (RCC) is 60% complete.

Read full summary

A and O EMINENTE is an SRA-sanctioned project by Ashapura Housing Private Limited in Dahisar, Mumbai 400068, registered with MahaRERA as P51800005475. It was launched in August 2017. It has 576 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2027, extended by 5 years 10 months from the original June 2021. Construction: excavation 93% complete, structure (RCC) 60% complete, final finishes 15% complete.

576 units booked out of total 576 units (100%). Since the December 2024 update, 97 more units have been booked and the possession date has moved from June 2021 to April 2027.