Yura Business Park, Andheri West
Ready to move
by Yura Business Park Private Limited · Andheri West, Mumbai 400058 · Map
- Launched
- Aug 2017First of 2 phases
- Possession (MahaRERA)
- Dec 2027Extended in 1 of 2 phases
- Concrete structure
- 100%Weighted across 2 phases
- Booked
- 74 of 8389% · 73 in Jul 2026
- Buildings
- 20.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 83
- Total units
- 83
- Buildings
- 2
- Land
- 0.3 acres
- Phases
- 2
- MahaRERA complaints
- 0
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Yura Business Park Ready to move | P51800005547 | 0 | 100% | 92% | |
| Yura Business Park - Phase 2 Ready to move | P51800079976 | 0 | 100% | 83% |
Show updates by phase
Yura Business Park (P51800005547)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 54 | |
| 100% | 100% | 0% | 53 | |
| 100% | 0% | 0% | 48 | |
| 70% | 0% | 0% | 39 |
"–" means MahaRERA shows no figure for that update.
Yura Business Park - Phase 2 (P51800079976)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 20 | |
| 100% | 100% | 0% | 20 | |
| 100% | 15% | 0% | 5 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Yura Business Park by Yura Business Park Private Limited is an 83-unit SRA-sanctioned project in Andheri West, Mumbai 400058, registered with MahaRERA in 2 phases, with possession due in December 2027. 74 units booked out of total 83 units. The concrete structure (RCC) is complete.
Read full summary
Yura Business Park is an SRA-sanctioned project by Yura Business Park Private Limited in Andheri West, Mumbai 400058, registered with MahaRERA as 2 phases (P51800005547, P51800079976). The first phase was launched in August 2017. Together the phases have 83 units in 2 buildings, as registered with MahaRERA. Both phases are active on MahaRERA.
The registered possession date is December 2027; 1 of 2 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 100% complete. Both phases have their structure complete.
74 units booked out of total 83 units (89%). Since the July 2026 update, 1 more unit has been booked.