Mahatma Jyotiba Phule Chs Ltd, Mulund East
by Tridevh Construction Company · Mulund East, Mumbai 400081 · Map
- Launched
- Aug 20176 yrs 4 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 3 yrs 4 mths
- Concrete structure
- 58%Mid-construction
- Booked
- 114 of 13286%
- Buildings
- 21.2 acres
- MahaRERA complaints
- 5Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 30
- 2 BHK
- 66
- 3 BHK
- 36
- Total units
- 132
- Buildings
- 2
- Land
- 1.2 acres
- Phases
- 1
- MahaRERA complaints
- 5
- Reserved units
- 16
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 58% | 52% | 114 | |
| 100% | 60% | 52% | 114 | |
| 100% | 60% | 52% | 114 | |
| 100% | 60% | 52% | 114 |
"–" means MahaRERA shows no figure for that update.
About this project
Mahatma Jyotiba Phule Chs Ltd by Tridevh Construction Company is a 132-unit BMC-sanctioned project in Mulund East, Mumbai 400081, launched in August 2017 with possession due in April 2027. 114 units booked out of total 132 units. The concrete structure (RCC) is 58% complete.
Read full summary
Mahatma Jyotiba Phule Chs Ltd is a BMC-sanctioned project by Tridevh Construction Company in Mulund East, Mumbai 400081, registered with MahaRERA as P51800006009. It was launched in August 2017. It has 132 units in 2 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2027, extended by 3 years 4 months from the original December 2023. Construction: excavation complete, structure (RCC) 58% complete, final finishes 52% complete.
114 units booked out of total 132 units (86%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 60% to 58% and the possession date has moved from December 2024 to April 2027.