Elite Tower, Borivali East

by Elite Construction Co · Borivali East, Mumbai 400066 · Map

Launched
Aug 20176 yrs 11 mths originally promised
Possession (MahaRERA)
Dec 2027Extended by 3 yrs 5 mths
Concrete structure
75%Mid-construction
Booked
187 of 25573%
Buildings
40.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
255
Total units
255
Buildings
4
Land
0.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation75%
Concrete structure (slabs)75%
Finishes, lifts and services70%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Jul 2026Oct 2026Dec 2024: Excavation 44%Jul 2026: Excavation 75%Oct 2026: Excavation 75%Dec 2024: Concrete structure (RCC) 38%Jul 2026: Concrete structure (RCC) 73%Oct 2026: Concrete structure (RCC) 75%Dec 2024: Final finishes 25%Jul 2026: Final finishes 48%Oct 2026: Final finishes 70%Excavation 75%Concrete structure (RCC) 75%Final finishes 70%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
75%75%70%187
75%73%48%–
44%38%25%187

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Elite Tower by Elite Construction Co is a 255-unit SRA-sanctioned project in Borivali East, Mumbai 400066, launched in August 2017 with possession due in December 2027. 187 units booked out of total 255 units. The concrete structure (RCC) is 75% complete.

Read full summary

Elite Tower is an SRA-sanctioned project by Elite Construction Co in Borivali East, Mumbai 400066, registered with MahaRERA as P51800006103. It was launched in August 2017. It has 255 units in 4 buildings, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, extended by 3 years 5 months from the original July 2024. Construction: excavation 75% complete, structure (RCC) 75% complete, final finishes 70% complete.

187 units booked out of total 255 units (73%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 73% to 75% and the possession date has moved from July 2025 to December 2027.