Aristocrate, Andheri East
by Amit Sudhir Dhadda · Andheri East, Mumbai 400069 · Map
- Launched
- Aug 20174 yrs 7 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 5 yrs 9 mths
- Concrete structure
- 40%Mid-construction
- Booked (free sale)
- 6 of 1056% · 8 rehab units
- Buildings
- 10.7 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale6 booked out of 105 units
Rehab8 units for existing members
Total 113 units. Rehab units are not for sale.
Project facts
- Other units
- 113
- Total units
- 113
- Buildings
- 1
- Land
- 0.7 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 105
- Rehab units
- 8
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 40% | 30% | 6 | |
| 100% | 40% | 30% | 6 | |
| 100% | 40% | 30% | – | |
| 100% | 40% | 30% | 6 |
"–" means MahaRERA shows no figure for that update.
About this project
Aristocrate by Amit Sudhir Dhadda is a 113-unit BMC-sanctioned project in Andheri East, Mumbai 400069, launched in August 2017 with possession due in December 2027. 6 units booked out of 105 units for sale. The concrete structure (RCC) is 40% complete.
Read full summary
Aristocrate is a BMC-sanctioned project by Amit Sudhir Dhadda in Andheri East, Mumbai 400069, registered with MahaRERA as P51800006105. It was launched in August 2017. It has 113 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 113 units, 105 are for sale and 8 are rehab units for existing members.
Its registered possession date is December 2027, extended by 5 years 9 months from the original March 2022. Construction: excavation complete, structure (RCC) 40% complete, final finishes 30% complete.
6 units booked out of 105 units for sale (6%).