The Zone, Borivali West
by Ms Amann Raj Housing And Development Corporation · Borivali West, Mumbai 400092 · Map
- Launched
- Aug 20173 yrs 5 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 5 yrs 11 mths
- Concrete structure
- 100%Nearing possession
- Booked
- 54 of 54100% · 53 in Jul 2026
- Buildings
- 10.3 acres
- MahaRERA complaints
- 5Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 54
- Total units
- 54
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 5
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 40% | 54 | |
| 100% | 100% | 20% | 53 | |
| 100% | 100% | 0% | 52 | |
| 100% | 0% | 0% | 47 |
"–" means MahaRERA shows no figure for that update.
About this project
The Zone by Ms Amann Raj Housing And Development Corporation is a 54-unit SRA-sanctioned project in Borivali West, Mumbai 400092, launched in August 2017 with possession due in December 2026. 54 units booked out of total 54 units. The concrete structure (RCC) is complete.
Read full summary
The Zone is an SRA-sanctioned project by Ms Amann Raj Housing And Development Corporation in Borivali West, Mumbai 400092, registered with MahaRERA as P51800006553. It was launched in August 2017. It has 54 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 5 years 11 months from the original January 2021. Construction: excavation complete, structure (RCC) complete, final finishes 40% complete.
54 units booked out of total 54 units (100%). Since the July 2026 update, 1 more unit has been booked and the possession date has moved from January 2022 to December 2026.