by Raunak Jigna Associates · Sion, Mumbai 400022 · Map

Launched
Aug 2017First of 2 phases
Possession (MahaRERA)
Apr 2027 – Dec 2028Not extended
Concrete structure
27%Weighted across 2 phases
Booked
492 of 56387% · 487 in Jul 2026
Buildings
40.3 acres
MahaRERA complaints
7Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
54
2 BHK
418
3 BHK
75
Other units
16
Total units
563
Buildings
4
Land
0.3 acres
Phases
2
MahaRERA complaints
7

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Raunak Centrum
Mid-construction
P5180000670520933%97%
Raunak Centrum - A
Mid-construction
P5180003326933823%81%
Show updates by phase

Raunak Centrum (P51800006705)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%33%0%207
100%33%0%208
100%33%0%206
100%33%0%207

"–" means MahaRERA shows no figure for that update.

Raunak Centrum - A (P51800033269)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%23%0%285
100%16%0%279
100%10%0%235
100%0%0%200

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)27%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 13%Dec 2025: Concrete structure (RCC) 19%Jul 2026: Concrete structure (RCC) 22%Oct 2026: Concrete structure (RCC) 27%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 27%Final finishes 0%

How to read construction stages

About this project

Raunak Centrum by Raunak Jigna Associates is a 563-unit SRA-sanctioned project in Sion, Mumbai 400022, registered with MahaRERA in 2 phases, with possession dates from April 2027 to December 2028. 492 units booked out of total 563 units. The concrete structure (RCC) is 27% complete.

Read full summary

Raunak Centrum is an SRA-sanctioned project by Raunak Jigna Associates in Sion, Mumbai 400022, registered with MahaRERA as 2 phases (P51800006705, P51800033269). The first phase was launched in August 2017. Together the phases have 563 units in 4 buildings: 547 homes (1, 2 and 3 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Both phases are active on MahaRERA.

The phases' registered possession dates run from April 2027 to December 2028; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 27% complete and final finishes 0% complete. Neither phase has its structure complete.

492 units booked out of total 563 units (87%). Since the July 2026 update, 5 more units have been booked.