34 Park Estate, Goregaon West

by M/S Reddy Builders & Developers · Goregaon West, Mumbai 400062 · Map

Launched
Aug 201710 yrs 11 mths promised
Possession (MahaRERA)
Jul 2028Not extended
Concrete structure
52%Mid-construction
Booked
959 of 1,28575%
Buildings
74.8 acres
MahaRERA complaints
21Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
564
2 BHK
569
3 BHK
152
Total units
1,285
Buildings
7
Land
4.8 acres
Phases
1
MahaRERA complaints
21

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation57%
Concrete structure (slabs)52%
Finishes, lifts and services37%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 57%Dec 2025: Excavation 57%Jul 2026: Excavation 57%Oct 2026: Excavation 57%Dec 2024: Concrete structure (RCC) 57%Dec 2025: Concrete structure (RCC) 52%Jul 2026: Concrete structure (RCC) 52%Oct 2026: Concrete structure (RCC) 52%Dec 2024: Final finishes 31%Dec 2025: Final finishes 37%Jul 2026: Final finishes 37%Oct 2026: Final finishes 37%Excavation 57%Concrete structure (RCC) 52%Final finishes 37%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
57%52%37%959
57%52%37%–
57%52%37%–
57%57%31%959

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

34 Park Estate by M/S Reddy Builders & Developers is a 1,285-unit SRA-sanctioned project in Goregaon West, Mumbai 400062, launched in August 2017 with possession due in July 2028. 959 units booked out of total 1,285 units. The concrete structure (RCC) is 52% complete.

Read full summary

34 Park Estate is an SRA-sanctioned project by M/S Reddy Builders & Developers in Goregaon West, Mumbai 400062, registered with MahaRERA as P51800006729. It was launched in August 2017. It has 1,285 units in 7 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is July 2028, unchanged since launch. Construction: excavation 57% complete, structure (RCC) 52% complete, final finishes 37% complete.

959 units booked out of total 1,285 units (75%).