34 Park Estate, Goregaon West
by M/S Reddy Builders & Developers · Goregaon West, Mumbai 400062 · Map
- Launched
- Aug 201710 yrs 11 mths promised
- Possession (MahaRERA)
- Jul 2028Not extended
- Concrete structure
- 52%Mid-construction
- Booked
- 959 of 1,28575%
- Buildings
- 74.8 acres
- MahaRERA complaints
- 21Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 564
- 2 BHK
- 569
- 3 BHK
- 152
- Total units
- 1,285
- Buildings
- 7
- Land
- 4.8 acres
- Phases
- 1
- MahaRERA complaints
- 21
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 57% | 52% | 37% | 959 | |
| 57% | 52% | 37% | – | |
| 57% | 52% | 37% | – | |
| 57% | 57% | 31% | 959 |
"–" means MahaRERA shows no figure for that update.
About this project
34 Park Estate by M/S Reddy Builders & Developers is a 1,285-unit SRA-sanctioned project in Goregaon West, Mumbai 400062, launched in August 2017 with possession due in July 2028. 959 units booked out of total 1,285 units. The concrete structure (RCC) is 52% complete.
Read full summary
34 Park Estate is an SRA-sanctioned project by M/S Reddy Builders & Developers in Goregaon West, Mumbai 400062, registered with MahaRERA as P51800006729. It was launched in August 2017. It has 1,285 units in 7 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is July 2028, unchanged since launch. Construction: excavation 57% complete, structure (RCC) 52% complete, final finishes 37% complete.
959 units booked out of total 1,285 units (75%).