Skip to main content

Amber Empire, Chembur

by Amber Capro Private Limited · Chembur, Mumbai 400089 · Map

Launched
Aug 20171 yr 7 mths originally promised
Possession (MahaRERA)
Apr 2029Extended by 10 yrs 1 mth
Concrete structure
85%Mid-construction
Booked
1 of 1100%
Buildings
10.4 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
1
Total units
1
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)85%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 85%Dec 2025: Concrete structure (RCC) 85%Jul 2026: Concrete structure (RCC) 85%Oct 2026: Concrete structure (RCC) 85%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 85%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%85%0%1
100%85%0%1
100%85%0%–
100%85%0%52

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Amber Empire by Amber Capro Private Limited is a 1-unit SRA-sanctioned project in Chembur, Mumbai 400089, launched in August 2017 with possession due in April 2029. 1 unit booked out of total 1 unit. The concrete structure (RCC) is 85% complete.

Read full summary

Amber Empire is an SRA-sanctioned project by Amber Capro Private Limited in Chembur, Mumbai 400089, registered with MahaRERA as P51800006968. It was launched in August 2017. It has 1 unit in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2029, extended by 10 years 1 month from the original March 2019. Construction: excavation complete, structure (RCC) 85% complete, final finishes not started.

1 unit booked out of total 1 unit (100%).