Sbi Ragvihar Chs, Borivali West

by Tuvin Consultancy LLP · Borivali West, Mumbai 400092 · Map

Launched
Aug 20173 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2027Extended by 7 yrs
Concrete structure
100%Nearing possession
Booked (free sale)
9 of 1464%
Buildings
20.2 acres
MahaRERA complaints
5Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale9 booked out of 14 units

Land-owner share14 units, not for sale

Total 28 units. Land-owner units are not for sale.

Project facts

1 RK
3
1 BHK
9
2 BHK
9
3 BHK
6
4 BHK
1
Total units
28
Buildings
2
Land
0.2 acres
Phases
1
MahaRERA complaints
5
Reserved units
3
Free-sale units
14
Land-owner share (not for sale)
14

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services40%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 88%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 40%Jul 2026: Final finishes 40%Oct 2026: Final finishes 40%Excavation 100%Concrete structure (RCC) 100%Final finishes 40%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%40%9
100%100%40%9
100%100%40%8
100%88%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400092

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400092
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 4 mths4 yrs 10 mths
Possession date extendedBy 7 yrs5 of 6
Possession date (MahaRERA)Dec 2027Jan 2027
Concrete structure (RCC)100%55%
Units booked (free sale)64%42%
MahaRERA complaints (filed by or against the builder)50

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Sbi Ragvihar Chs by Tuvin Consultancy LLP is a 28-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in August 2017 with possession due in December 2027. 9 units booked out of 14 units for sale. The concrete structure (RCC) is complete.

Read full summary

Sbi Ragvihar Chs is a BMC-sanctioned project by Tuvin Consultancy LLP in Borivali West, Mumbai 400092, registered with MahaRERA as P51800007223. It was launched in August 2017. It has 28 units in 2 buildings, with 1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 28 units, 14 are for sale and 14 are the land-owner's share, not for sale.

Its registered possession date is December 2027, extended by 7 years from the original December 2020. Construction: excavation complete, structure (RCC) complete, final finishes 40% complete.

9 units booked out of 14 units for sale (64%).