The Heights, Andheri East
by Dhruvi Properties Pvt Ltd · Andheri East, Mumbai 400059 · Map
- Launched
- Aug 20173 yrs 10 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 5 yrs 10 mths
- Concrete structure
- 90%Mid-construction
- Booked
- 90 of 9199%
- Buildings
- 21.2 acres
- MahaRERA complaints
- 7Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 21
- 2 BHK
- 40
- 3 BHK
- 16
- Other units
- 14
- Total units
- 91
- Buildings
- 2
- Land
- 1.2 acres
- Phases
- 1
- MahaRERA complaints
- 7
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 90% | 50% | 90 | |
| 67% | 60% | 33% | – | |
| 67% | 60% | 33% | – | |
| 100% | 90% | 50% | 90 |
"–" means MahaRERA shows no figure for that update.
About this project
The Heights by Dhruvi Properties Pvt Ltd is a 91-unit project in Andheri East, Mumbai 400059, launched in August 2017 with possession due in April 2027. 90 units booked out of total 91 units. The concrete structure (RCC) is 90% complete.
Read full summary
The Heights is a project by Dhruvi Properties Pvt Ltd in Andheri East, Mumbai 400059, registered with MahaRERA as P51800007232. It was launched in August 2017. It has 91 units in 2 buildings: 77 homes (1, 2 and 3 BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2027, extended by 5 years 10 months from the original June 2021. Construction: excavation complete, structure (RCC) 90% complete, final finishes 50% complete.
90 units booked out of total 91 units (99%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 60% to 90% and the possession date has moved from December 2024 to April 2027.