Mars- Suncity Housing Phase II, Powai
by Suncity Housing · Powai, Mumbai 400076 · Map
- Launched
- Aug 20179 yrs 4 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Nearing possession
- Booked
- 207 of 23389%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 115
- 2 BHK
- 118
- Total units
- 233
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 80% | 207 | |
| 100% | 100% | 0% | 207 | |
| 100% | 97% | 0% | 206 | |
| 100% | 0% | 0% | 242 |
"–" means MahaRERA shows no figure for that update.
About this project
Mars- Suncity Housing Phase II by Suncity Housing is a 233-unit BMC-sanctioned project in Powai, Mumbai 400076, launched in August 2017 with possession due in December 2026. 207 units booked out of total 233 units. The concrete structure (RCC) is complete.
Read full summary
Mars- Suncity Housing Phase II is a BMC-sanctioned project by Suncity Housing in Powai, Mumbai 400076, registered with MahaRERA as P51800007268. It was launched in August 2017. It has 233 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.
207 units booked out of total 233 units (89%).