Saffron Residency Phase -1, Kurla East

Ready to move

by Ayodhya Construction Co · Kurla East, Mumbai 400024 · Map

Launched
Aug 20175 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2023Extended by 1 yr
Concrete structure
100%Ready to move
Booked
–
Buildings
41.7 acres
MahaRERA complaints
6Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
36
1 BHK
90
2 BHK
108
3 BHK
36
Other units
17
Total units
287
Buildings
4
Land
1.7 acres
Phases
1
MahaRERA complaints
6

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 90%Dec 2025: Final finishes 90%Jul 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%–
100%100%90%–
100%100%90%220

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Saffron Residency Phase -1 by Ayodhya Construction Co is a 287-unit project in Kurla East, Mumbai 400024, launched in August 2017 with possession due in December 2023. The concrete structure (RCC) is complete.

Read full summary

Saffron Residency Phase -1 is a project by Ayodhya Construction Co in Kurla East, Mumbai 400024, registered with MahaRERA as P51800007485. It was launched in August 2017. It has 287 units in 4 buildings: 270 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 17 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in December 2023, after an extension of 1 year from the original December 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.