Buddha Vihar Chs Ltd, Kurla West
by M/S Regal Builders And Developers · Kurla West, Mumbai 400070 · Map
- Launched
- Aug 20179 yrs 4 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Nearing possession
- Booked
- 56 of 6093%
- Buildings
- 11.4 acres
- MahaRERA complaints
- 3Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 54
- Other units
- 6
- Total units
- 60
- Buildings
- 1
- Land
- 1.4 acres
- Phases
- 1
- MahaRERA complaints
- 3
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 80% | 56 | |
| 100% | 100% | 80% | 56 | |
| 100% | 100% | 80% | 56 | |
| 100% | 100% | 80% | 55 |
"–" means MahaRERA shows no figure for that update.
About this project
Buddha Vihar Chs Ltd by M/S Regal Builders And Developers is a 60-unit SRA-sanctioned project in Kurla West, Mumbai 400070, launched in August 2017 with possession due in December 2026. 56 units booked out of total 60 units. The concrete structure (RCC) is complete.
Read full summary
Buddha Vihar Chs Ltd is an SRA-sanctioned project by M/S Regal Builders And Developers in Kurla West, Mumbai 400070, registered with MahaRERA as P51800007510. It was launched in August 2017. It has 60 units in 1 building: 54 homes (1 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.
56 units booked out of total 60 units (93%).