Skip to main content

Trinity Towers, Powai

by Parorch Developers LLP · Powai, Mumbai 400076 · Map

Launched
Aug 20179 yrs 4 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
0%Early stage
Booked
39 of 12531%
Buildings
10.8 acres
MahaRERA complaints
4Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
62
4 BHK
61
5+ BHK
2
Total units
125
Buildings
1
Land
0.8 acres
Phases
1
MahaRERA complaints
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation70%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 70%Dec 2025: Excavation 70%Jul 2026: Excavation 70%Oct 2026: Excavation 70%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 70%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
70%0%0%39
70%0%0%–
70%0%0%–
70%0%0%39

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Trinity Towers by Parorch Developers LLP is a 125-unit project in Powai, Mumbai 400076, launched in August 2017 with possession due in December 2026. 39 units booked out of total 125 units. Work on the concrete structure (RCC) has not started.

Read full summary

Trinity Towers is a project by Parorch Developers LLP in Powai, Mumbai 400076, registered with MahaRERA as P51800008384. It was launched in August 2017. It has 125 units in 1 building, with 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation 70% complete, structure (RCC) not started, final finishes not started.

39 units booked out of total 125 units (31%).