Mulund Hemant Chs, Mulund West
by Confident Real Estate Private Limited · Mulund West, Mumbai 400080 · Map
- Launched
- Aug 20173 yrs 1 mth originally promised
- Possession (MahaRERA)
- Jun 2027Extended by 6 yrs 9 mths
- Concrete structure
- 63%Mid-construction
- Booked
- –
- Buildings
- 20.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 4
- 2 BHK
- 3
- Other units
- 3
- Total units
- 10
- Buildings
- 2
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 63% | 0% | 15 | |
| 100% | 63% | 0% | – | |
| 100% | 63% | 0% | – | |
| 100% | 63% | 0% | 15 |
"–" means MahaRERA shows no figure for that update.
About this project
Mulund Hemant Chs by Confident Real Estate Private Limited is a 10-unit project in Mulund West, Mumbai 400080, launched in August 2017 with possession due in June 2027. The concrete structure (RCC) is 63% complete.
Read full summary
Mulund Hemant Chs is a project by Confident Real Estate Private Limited in Mulund West, Mumbai 400080, registered with MahaRERA as P51800008865. It was launched in August 2017. It has 10 units in 2 buildings: 7 homes (1 and 2 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is June 2027, extended by 6 years 9 months from the original September 2020. Construction: excavation complete, structure (RCC) 63% complete, final finishes not started.