Silver Springs, Andheri East
by Shrikrishna Developers · Andheri East, Mumbai 400069 · Map
- Launched
- Aug 20174 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 6 yrs
- Concrete structure
- 100%Nearing possession
- Booked
- 31 of 7541%
- Buildings
- 10.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 36
- 2 BHK
- 35
- Other units
- 4
- Total units
- 75
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 80% | 31 | |
| 100% | 100% | 80% | – | |
| 100% | 100% | 80% | – | |
| 100% | 100% | 80% | 31 |
"–" means MahaRERA shows no figure for that update.
About this project
Silver Springs by Shrikrishna Developers is a 75-unit BMC-sanctioned project in Andheri East, Mumbai 400069, launched in August 2017 with possession due in December 2027. 31 units booked out of total 75 units. The concrete structure (RCC) is complete.
Read full summary
Silver Springs is a BMC-sanctioned project by Shrikrishna Developers in Andheri East, Mumbai 400069, registered with MahaRERA as P51800009204. It was launched in August 2017. It has 75 units in 1 building: 71 homes (1 and 2 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, extended by 6 years from the original December 2021. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.
31 units booked out of total 75 units (41%).