Lake Riviera, Chandivali

by Pashmina Realty Private Limited · Chandivali, Mumbai 400072 · Map

Launched
Aug 2017First of 3 phases
Possession (MahaRERA)
Dec 2025 – Apr 2028Extended in 2 of 3 phases
Concrete structure
39%Weighted across 3 phases
Booked
–
Buildings
40.2 acres
MahaRERA complaints
69Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
226
3 BHK
133
Total units
359
Buildings
4
Land
0.2 acres
Phases
3
MahaRERA complaints
69

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Lake Riviera Wing A And B
Mid-construction Lapsed
P5180000935317160%73%
Lake Riviera Wing C
Mid-construction
P518000184807550%75%
Lake Riviera Wing D
Early stage
P518000483541130%–
Show updates by phase

Lake Riviera Wing A And B (P51800009353)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%60%92%125
100%60%85%124
100%60%85%124
75%60%0%128

"–" means MahaRERA shows no figure for that update.

Lake Riviera Wing C (P51800018480)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%50%0%56
100%50%0%56
100%50%0%56
90%0%0%57

"–" means MahaRERA shows no figure for that update.

Lake Riviera Wing D (P51800048354)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%–
0%0%0%–
0%0%0%–
0%0%0%0

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation69%
Concrete structure (slabs)39%
Finishes, lifts and services44%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 55%Dec 2025: Excavation 69%Jul 2026: Excavation 69%Oct 2026: Excavation 69%Dec 2024: Concrete structure (RCC) 29%Dec 2025: Concrete structure (RCC) 39%Jul 2026: Concrete structure (RCC) 39%Oct 2026: Concrete structure (RCC) 39%Dec 2024: Final finishes 0%Dec 2025: Final finishes 40%Jul 2026: Final finishes 40%Oct 2026: Final finishes 44%Excavation 69%Final finishes 44%Concrete structure (RCC) 39%

How to read construction stages

About this project

Lake Riviera by Pashmina Realty Private Limited is a 359-unit SRA-sanctioned project in Chandivali, Mumbai 400072, registered with MahaRERA in 3 phases, with possession dates from December 2025 to April 2028. The concrete structure (RCC) is 39% complete.

Read full summary

Lake Riviera is an SRA-sanctioned project by Pashmina Realty Private Limited in Chandivali, Mumbai 400072, registered with MahaRERA as 3 phases (P51800009353, P51800018480, P51800048354). The first phase was launched in August 2017. Together the phases have 359 units in 4 buildings, with 2 and 3 BHK homes as registered with MahaRERA. On MahaRERA, 2 are active and 1 is lapsed.

The phases' registered possession dates run from December 2025 to April 2028; 2 of 3 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 39% complete and final finishes 44% complete. None of the 3 phases has its structure complete.