Lake Riviera, Chandivali
by Pashmina Realty Private Limited · Chandivali, Mumbai 400072 · Map
- Launched
- Aug 2017First of 3 phases
- Possession (MahaRERA)
- Dec 2025 – Apr 2028Extended in 2 of 3 phases
- Concrete structure
- 39%Weighted across 3 phases
- Booked
- –
- Buildings
- 40.2 acres
- MahaRERA complaints
- 69Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 226
- 3 BHK
- 133
- Total units
- 359
- Buildings
- 4
- Land
- 0.2 acres
- Phases
- 3
- MahaRERA complaints
- 69
The 3 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Lake Riviera Wing A And B Mid-construction Lapsed | P51800009353 | 171 | 60% | 73% | |
| Lake Riviera Wing C Mid-construction | P51800018480 | 75 | 50% | 75% | |
| Lake Riviera Wing D Early stage | P51800048354 | 113 | 0% | – |
Show updates by phase
Lake Riviera Wing A And B (P51800009353)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 60% | 92% | 125 | |
| 100% | 60% | 85% | 124 | |
| 100% | 60% | 85% | 124 | |
| 75% | 60% | 0% | 128 |
"–" means MahaRERA shows no figure for that update.
Lake Riviera Wing C (P51800018480)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 50% | 0% | 56 | |
| 100% | 50% | 0% | 56 | |
| 100% | 50% | 0% | 56 | |
| 90% | 0% | 0% | 57 |
"–" means MahaRERA shows no figure for that update.
Lake Riviera Wing D (P51800048354)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Lake Riviera by Pashmina Realty Private Limited is a 359-unit SRA-sanctioned project in Chandivali, Mumbai 400072, registered with MahaRERA in 3 phases, with possession dates from December 2025 to April 2028. The concrete structure (RCC) is 39% complete.
Read full summary
Lake Riviera is an SRA-sanctioned project by Pashmina Realty Private Limited in Chandivali, Mumbai 400072, registered with MahaRERA as 3 phases (P51800009353, P51800018480, P51800048354). The first phase was launched in August 2017. Together the phases have 359 units in 4 buildings, with 2 and 3 BHK homes as registered with MahaRERA. On MahaRERA, 2 are active and 1 is lapsed.
The phases' registered possession dates run from December 2025 to April 2028; 2 of 3 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 39% complete and final finishes 44% complete. None of the 3 phases has its structure complete.