Gajanan Plaza, Kandivali West

Ready to move

by Balaji Construction Co · Kandivali West, Mumbai 400067 · Map

Launched
Aug 20171 yr 4 mths originally promised
Possession (MahaRERA)
Apr 2020Extended by 1 yr 4 mths
Concrete structure
100%Ready to move
Booked
–
Buildings
10.1 acres
MahaRERA complaints
14Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
38
Total units
38
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
14

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 95%Dec 2025: Final finishes 95%Jul 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%–
100%100%95%–
100%100%95%8

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Gajanan Plaza by Balaji Construction Co is a 38-unit project in Kandivali West, Mumbai 400067, launched in August 2017 with possession due in April 2020. The concrete structure (RCC) is complete.

Read full summary

Gajanan Plaza is a project by Balaji Construction Co in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800009622. It was launched in August 2017. It has 38 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in April 2020, after an extension of 1 year 4 months from the original December 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.