Sai Swayam, Mankhurd

by Joinwood Reality Private Limited · Mankhurd, Mumbai 400088 · Map

Launched
Aug 20174 yrs 4 mths originally promised
Possession (MahaRERA)
Apr 2027Extended by 5 yrs 4 mths
Concrete structure
100%Nearing possession
Booked
40 of 7752%
Buildings
10.5 acres
MahaRERA complaints
6Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
25
2 BHK
25
3 BHK
26
4 BHK
1
Total units
77
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
6

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services70%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 56%Dec 2025: Concrete structure (RCC) 56%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 70%Oct 2026: Final finishes 70%Excavation 100%Concrete structure (RCC) 100%Final finishes 70%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%70%40
100%100%70%40
100%56%0%41
100%56%0%41

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Sai Swayam by Joinwood Reality Private Limited is a 77-unit BMC-sanctioned project in Mankhurd, Mumbai 400088, launched in August 2017 with possession due in April 2027. 40 units booked out of total 77 units. The concrete structure (RCC) is complete.

Read full summary

Sai Swayam is a BMC-sanctioned project by Joinwood Reality Private Limited in Mankhurd, Mumbai 400088, registered with MahaRERA as P51800009824. It was launched in August 2017. It has 77 units in 1 building, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2027, extended by 5 years 4 months from the original December 2021. Construction: excavation complete, structure (RCC) complete, final finishes 70% complete.

40 units booked out of total 77 units (52%).