Ready to move

by N N Datar & Associates · Ghatkopar West, Mumbai 400086 · Map

Launched
Aug 20175 yrs 4 mths originally promised
Possession (MahaRERA)
Apr 2028Extended by 5 yrs 4 mths
Concrete structure
100%Ready to move
Booked
59 of 11153% · 49 in Jul 2026
Buildings
10.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
111
Total units
111
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services99%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 35%Dec 2025: Final finishes 97%Jul 2026: Final finishes 99%Oct 2026: Final finishes 99%Excavation 100%Concrete structure (RCC) 100%Final finishes 99%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%99%59
100%100%99%49
100%100%97%37
100%100%35%17

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Biz Point by N N Datar & Associates is a 111-unit BMC-sanctioned project in Ghatkopar West, Mumbai 400086, launched in August 2017 with possession due in April 2028. 59 units booked out of total 111 units. The concrete structure (RCC) is complete.

Read full summary

Biz Point is a BMC-sanctioned project by N N Datar & Associates in Ghatkopar West, Mumbai 400086, registered with MahaRERA as P51800009838. It was launched in August 2017. It has 111 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2028, extended by 5 years 4 months from the original December 2022. Construction: excavation complete, structure (RCC) complete, final finishes 99% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

59 units booked out of total 111 units (53%). Since the July 2026 update, 10 more units have been booked and the possession date has moved from December 2023 to April 2028.